Client
The Archdiocese of Brisbane
The Archdiocese of Brisbane
January 2017
Beaudesert QLD
Construct Only
$3.5m
Alder Constructions were contracted to complete the bulk earthworks, reinforced block and rock retaining walls, preparation of building pads, civil services, pavement construction for carparks, concrete driveways and footpaths, irrigation and turfing of the sporting oval and running track for the new McAuley College School.
Major bulk earthworks of over 60,000m³ Cut to Fill was required, and an additional 25,000m³ of imported material to provide for the new levels required. GPS controlled machinery was used in order to increase works productivity, and to achieve the tolerances required to the building pads and oval. All required civil works were completed ahead of schedule by Alder Constructions for handover to building contractors for all works to be completed ahead of the new school term.